00:00:01.030 --> 00:00:02.890
Hi, well, it's 10:32.
00:00:02.890 --> 00:00:05.480
So I'm gonna call this meeting to order.
00:00:05.480 --> 00:00:07.710
Good morning, everyone.
00:00:07.710 --> 00:00:09.400
My name is Kasey Feldman-Thomason.
00:00:09.400 --> 00:00:13.390
I'll be presiding over this hearing
00:00:13.390 --> 00:00:15.350
for the Public Utility Commission.
00:00:15.350 --> 00:00:16.940
Thank you for coming.
00:00:16.940 --> 00:00:19.696
I want to convene this hearing
00:00:19.696 --> 00:00:22.480
and project 38533 the PUC review
00:00:22.480 --> 00:00:27.110
for ERCOT budget for 2022, 2023.
00:00:27.110 --> 00:00:31.700
The agenda for this morning
is that ERCOT has presentation
00:00:31.700 --> 00:00:34.680
that they'd like to make
after that we'll open the floor
00:00:34.680 --> 00:00:37.530
for any questions that
anyone might have,
00:00:37.530 --> 00:00:40.210
but I don't see anyone
who might have questions.
00:00:40.210 --> 00:00:43.270
I may have a couple
of follow-up questions
00:00:43.270 --> 00:00:48.270
and then we'll take it from
there and close the workshop
00:00:49.770 --> 00:00:52.150
once any questions are answered
00:00:53.240 --> 00:00:56.800
and I'll go ahead
and turn it over to y'all
00:00:56.800 --> 00:00:58.110
Brad and Sean.
00:00:58.110 --> 00:00:59.470
Great, thank you.
00:00:59.470 --> 00:01:00.950
I appreciate that.
00:01:00.950 --> 00:01:02.180
Good morning, this is Brad Jones,
00:01:02.180 --> 00:01:05.010
interim president and CEO of ERCOT
00:01:05.010 --> 00:01:07.270
sitting with me here is Sean Taylor,
00:01:07.270 --> 00:01:10.280
vice president and
chief financial officer,
00:01:10.280 --> 00:01:14.620
ERCOT submitted its
2022, 2023 biennium report
00:01:14.620 --> 00:01:19.040
on September 21st of 2021.
00:01:19.040 --> 00:01:21.090
The highlight of that
submission is that we intend
00:01:21.090 --> 00:01:24.547
to maintain our system
admin fee at a rate of $0.555,
00:01:26.270 --> 00:01:29.200
per megawatt hour, which
is where it stands today
00:01:29.200 --> 00:01:32.610
which is where it has stood since 2016.
00:01:32.610 --> 00:01:37.453
At the time of our 2016,
2017 biennium budget request.
00:01:39.870 --> 00:01:43.860
We indicated at that time
that we would be able to hold
00:01:43.860 --> 00:01:47.300
that rate for a period
of four to six years.
00:01:47.300 --> 00:01:49.510
It is currently anticipated
00:01:49.510 --> 00:01:53.820
that there is no fee
increase for this year.
00:01:53.820 --> 00:01:58.820
So that would make the 2022
and 2023 cycle the eighth year
00:02:00.670 --> 00:02:03.733
that we have held our
admin fee at the same level.
00:02:05.850 --> 00:02:08.040
ERCOT management
and the board of directors
00:02:08.040 --> 00:02:11.730
have supported the
reasonableness of this budget request
00:02:11.730 --> 00:02:15.670
to provide for our operations
for the next two years.
00:02:15.670 --> 00:02:18.550
At the outset, I'd like to
thank the Commission's staff
00:02:19.640 --> 00:02:22.850
for their collaboration in the
budget development process,
00:02:22.850 --> 00:02:26.090
because it ensures that
we prepare a budget request
00:02:26.090 --> 00:02:27.670
for the board's consideration
00:02:27.670 --> 00:02:31.210
that also includes the
Commission's priorities.
00:02:31.210 --> 00:02:33.100
At a high level, the budget includes
00:02:33.100 --> 00:02:37.817
a spinning authorization
of 322 million for 2022
00:02:38.950 --> 00:02:42.100
and 287 billion for 2023.
00:02:44.210 --> 00:02:47.990
Also included in this
budget request is funding
00:02:47.990 --> 00:02:52.990
for the NERC ERO Electric
Reliability Organization.
00:02:53.050 --> 00:02:54.840
This is a pass through.
00:02:54.840 --> 00:02:57.380
These are funds that
are not used by ERCOT
00:02:57.380 --> 00:02:59.240
for ERCOT operations,
00:02:59.240 --> 00:03:04.240
and is a total of $40.5
million for a period of two years
00:03:04.240 --> 00:03:06.363
for the entire two year biennium.
00:03:08.040 --> 00:03:08.873
In terms of revenue,
00:03:08.873 --> 00:03:12.680
the system admin fee remains
our primary funding source.
00:03:12.680 --> 00:03:16.780
And as I said, it is
projected under this request
00:03:16.780 --> 00:03:21.120
to be $0.555 per megawatt hour.
00:03:21.120 --> 00:03:26.060
The system admin fee will
generate 233 million for 2022
00:03:26.060 --> 00:03:30.100
and 241 million for 2023.
00:03:30.100 --> 00:03:32.530
In addition to the system admin fee,
00:03:32.530 --> 00:03:37.530
we also have user fees
pursuant to Commission rules.
00:03:37.970 --> 00:03:40.800
The user fees do not
cover a significant portion
00:03:40.800 --> 00:03:42.240
of our revenues.
00:03:42.240 --> 00:03:45.660
We expect approximately
20 million in 2022
00:03:45.660 --> 00:03:50.383
and 20 million, again in
2023, from those user fees.
00:03:51.960 --> 00:03:54.870
In regard to budget drivers
for this biennium budget,
00:03:54.870 --> 00:03:56.670
there are three primary drivers.
00:03:56.670 --> 00:04:01.350
First, the drivers to maintain
a flat system admin fee,
00:04:01.350 --> 00:04:04.133
which is really what
we're requesting today.
00:04:05.090 --> 00:04:09.680
Second it's to incorporate key
initiatives and new demands,
00:04:09.680 --> 00:04:13.120
and third to comply
with the board of directors
00:04:13.120 --> 00:04:15.160
debt strategy guidance.
00:04:15.160 --> 00:04:17.410
Let me start with the first driver.
00:04:17.410 --> 00:04:20.360
The system admin fee
as we have indicated,
00:04:20.360 --> 00:04:25.360
we intend to hold flat at 0.555
for the next two year cycle.
00:04:26.000 --> 00:04:29.470
A relative to 2022 amounts projected
00:04:29.470 --> 00:04:33.890
in the approved 2020
and 2021 by any amount.
00:04:33.890 --> 00:04:38.150
We expect a decrease in
system admin fee revenues
00:04:38.150 --> 00:04:41.110
due to lower than expected load growth,
00:04:41.110 --> 00:04:43.343
particularly associated with COVID.
00:04:44.710 --> 00:04:48.520
We also expect department
net expenditures to increase,
00:04:48.520 --> 00:04:52.660
and that's due to the cost
of inflation, Winter Storm Uri,
00:04:52.660 --> 00:04:55.380
legislative requirements,
and other due demands,
00:04:55.380 --> 00:04:57.913
partially offset by our cost savings.
00:04:59.140 --> 00:05:02.253
We expect project
expenditures to increase as well,
00:05:03.200 --> 00:05:05.730
and we'll maintain a
consistent multi-year approach
00:05:05.730 --> 00:05:07.730
that takes into account
the major refreshes
00:05:07.730 --> 00:05:09.653
we need to do, system refreshes.
00:05:11.130 --> 00:05:13.370
The budget request includes a revised
00:05:13.370 --> 00:05:16.520
real-time quantization
project expenditures
00:05:16.520 --> 00:05:19.190
to reflect the current project forecast.
00:05:19.190 --> 00:05:22.020
It also adds the met
center replacement project
00:05:22.020 --> 00:05:24.300
with an expected purchase of the office
00:05:24.300 --> 00:05:26.683
and meeting facility in 2022.
00:05:28.140 --> 00:05:30.660
Lastly, in regard to this first driver,
00:05:30.660 --> 00:05:34.220
we expect a significant
decrease in interest income
00:05:34.220 --> 00:05:36.493
due to much lower interest rates.
00:05:37.810 --> 00:05:39.790
For the second budget driver.
00:05:39.790 --> 00:05:43.100
We incorporated strategic
objectives and new demands,
00:05:43.100 --> 00:05:46.340
but we expect to
recognize efficiency savings
00:05:46.340 --> 00:05:49.860
to help offset some of the
costs of these new demands.
00:05:49.860 --> 00:05:52.700
ERCOT will incorporate
its strategic plan objectives
00:05:52.700 --> 00:05:56.290
by enhancing our operating
capabilities to maintain
00:05:56.290 --> 00:06:00.160
the reliability of an
increasingly complex system,
00:06:00.160 --> 00:06:02.290
improving our information exchange
00:06:02.290 --> 00:06:04.940
to facilitate collaborative interaction
00:06:04.940 --> 00:06:08.600
and advancing competitive
solutions for changing industry
00:06:08.600 --> 00:06:10.910
while optimizing the
use of ERCOT resources
00:06:10.910 --> 00:06:14.003
to provide high value
services continuously.
00:06:14.930 --> 00:06:17.060
Those are the key strategic objectives
00:06:18.230 --> 00:06:20.190
that were identified
in our strategic plan
00:06:20.190 --> 00:06:25.190
that was adopted in 2018
and runs through 2023.
00:06:25.450 --> 00:06:28.340
In addition to those
strategic objectives,
00:06:28.340 --> 00:06:29.850
there are many new demands
00:06:29.850 --> 00:06:33.330
that arose from winter
storm Uri and particular,
00:06:33.330 --> 00:06:37.690
the generation transmission
weatherization inspections,
00:06:37.690 --> 00:06:40.310
which have been required by legislation
00:06:40.310 --> 00:06:41.743
signed into law this year.
00:06:43.130 --> 00:06:46.440
The budget requests also
includes significant increases
00:06:46.440 --> 00:06:51.030
in company insurance,
external legal services,
00:06:51.030 --> 00:06:53.560
an additional
communication service costs
00:06:53.560 --> 00:06:56.080
across our industry.
00:06:56.080 --> 00:06:58.010
We have taken exceptional
measures to control
00:06:58.010 --> 00:07:01.020
and cut these costs
across the organization
00:07:01.020 --> 00:07:02.710
to offset those significant costs.
00:07:02.710 --> 00:07:04.743
However, not all costs could be offset.
00:07:06.000 --> 00:07:09.200
One last comment on
the topic of new demands,
00:07:09.200 --> 00:07:12.610
and that is in the 2020 to 2023 budget.
00:07:12.610 --> 00:07:15.430
We contemplate full
recovery of the generation
00:07:15.430 --> 00:07:17.790
and transmission inspection costs
00:07:17.790 --> 00:07:19.713
through additional user fees.
00:07:21.200 --> 00:07:24.230
The third and primary
budget driver is compliance
00:07:24.230 --> 00:07:27.080
with the board's debt strategy guidance.
00:07:27.080 --> 00:07:29.740
To do that, we will maintain or improve
00:07:29.740 --> 00:07:32.290
or cuts the longterm financial integrity
00:07:32.290 --> 00:07:36.010
by managing outstanding
debt and liquidity requirements,
00:07:36.010 --> 00:07:39.390
maintaining a fair, stable
and predictable fees
00:07:39.390 --> 00:07:42.130
by using debt matching
to the extent possible
00:07:42.130 --> 00:07:45.450
and providing the lowest cost matching
00:07:45.450 --> 00:07:48.710
lowest cost of system
administration fee payers
00:07:48.710 --> 00:07:50.760
by using the lowest cost debt
00:07:50.760 --> 00:07:52.770
that is available inappropriate.
00:07:52.770 --> 00:07:55.020
We continue to improve
operational efficiency
00:07:55.020 --> 00:07:59.560
to help keep the current
system admin fee rate level low
00:08:00.900 --> 00:08:03.270
and streamlined processes
and use technology
00:08:03.270 --> 00:08:06.600
where available to create
additional efficiencies.
00:08:06.600 --> 00:08:09.010
Those are my comments and we would both
00:08:09.010 --> 00:08:10.710
be happy to answer your questions.
00:08:11.580 --> 00:08:12.530
Great, thank you.
00:08:14.640 --> 00:08:17.730
And as there are no
members of the public here
00:08:17.730 --> 00:08:20.950
to ask questions, I'll just go ahead
00:08:20.950 --> 00:08:23.780
and no staff members except myself
00:08:23.780 --> 00:08:26.290
I will go ahead and ask my questions.
00:08:26.290 --> 00:08:29.130
So I heard you say in your presentation,
00:08:29.130 --> 00:08:33.440
and this also echoes the
filing and project 38533,
00:08:33.440 --> 00:08:38.110
that the budget request
contemplates full recovery
00:08:38.110 --> 00:08:40.180
of the Senate Bill 3 generation
00:08:40.180 --> 00:08:43.320
and transmission inspection costs.
00:08:43.320 --> 00:08:47.540
Does that cover all costs associated
00:08:47.540 --> 00:08:50.033
with the weatherization
mandates, for example,
00:08:53.310 --> 00:08:54.143
would it cover the cost
00:08:54.143 --> 00:08:56.503
of developing weatherization standards?
00:08:58.590 --> 00:09:01.970
So it is not contemplated to
cover that as it contemplate,
00:09:01.970 --> 00:09:04.028
just to cover the cost of inspections.
00:09:04.028 --> 00:09:04.861
Okay.
00:09:04.861 --> 00:09:05.870
We have already filed a notice
00:09:05.870 --> 00:09:07.490
of protocol revision requests,
00:09:07.490 --> 00:09:09.860
which includes an outlines those costs
00:09:09.860 --> 00:09:12.990
and is currently being discussed
among market participant.
00:09:12.990 --> 00:09:17.320
Okay, and so the
other costs besides
00:09:17.320 --> 00:09:22.060
those directly attributable
to the inspections,
00:09:22.060 --> 00:09:23.650
where do we find those in the budget?
00:09:23.650 --> 00:09:27.040
Those will be absorbed
within our normal budget.
00:09:27.040 --> 00:09:29.680
Okay, just operating
cost basically.
00:09:29.680 --> 00:09:30.513
Yes.
00:09:30.513 --> 00:09:34.930
Okay, and
additionally, in your filing,
00:09:34.930 --> 00:09:39.900
you state in the statement
of the ERCOT CEO,
00:09:39.900 --> 00:09:43.830
you state that ERCOT may
recommend other user fee changes
00:09:43.830 --> 00:09:48.830
to the board while this 2020
to 2023 budget is in effect.
00:09:50.540 --> 00:09:54.730
Other than the fee to
cover the inspections
00:09:54.730 --> 00:09:55.820
that we've just talked about.
00:09:55.820 --> 00:09:58.320
Are there any other
specific potential changes
00:09:58.320 --> 00:10:01.560
that are anticipated
or is that just something
00:10:01.560 --> 00:10:03.560
that could happen?
00:10:03.560 --> 00:10:05.180
It's just something
that could happen.
00:10:05.180 --> 00:10:09.510
Our normal process is trying
to minimize additional fees
00:10:09.510 --> 00:10:12.610
to capture most everything
within the system admin fee.
00:10:12.610 --> 00:10:15.320
And that's what we've done
here in this filing as well.
00:10:15.320 --> 00:10:20.070
We do have a fee for
wide area network use
00:10:20.070 --> 00:10:22.480
and that's one of our
larger fees that we have.
00:10:22.480 --> 00:10:26.230
Sean, are there others
that you'd like to highlight?
00:10:26.230 --> 00:10:27.940
There's nothing specifically
that I need to highlight,
00:10:27.940 --> 00:10:30.450
but there's also a times
we probably might remember
00:10:30.450 --> 00:10:33.830
from cybersecurity monitor
where there's PUC mandated things
00:10:33.830 --> 00:10:35.220
that come into play that we also
00:10:35.220 --> 00:10:37.130
would have develop fees for potentially.
00:10:37.130 --> 00:10:39.560
Okay, all right.
00:10:39.560 --> 00:10:42.150
Well, those are all of my questions.
00:10:42.150 --> 00:10:45.410
And thank you for answering them.
00:10:45.410 --> 00:10:47.850
We've appreciated working with you all.
00:10:47.850 --> 00:10:49.640
The process for
year is that I anticipate
00:10:49.640 --> 00:10:52.460
having a draft order
presented to the Commission
00:10:52.460 --> 00:10:54.623
at the December 2nd open meeting.
00:10:55.490 --> 00:10:57.500
If for some reason that's not possible,
00:10:57.500 --> 00:11:00.113
it'll be at the December
16th open meeting.
00:11:01.260 --> 00:11:05.990
The Commission will consider
your 2020 to 2023 budget
00:11:05.990 --> 00:11:08.860
and also provide some directives
00:11:08.860 --> 00:11:12.853
for the 2024, 2025 budget.
00:11:14.660 --> 00:11:18.623
So look for a draft order
next week and we'll keep,
00:11:20.000 --> 00:11:21.320
like I said, I anticipate
00:11:21.320 --> 00:11:23.563
it being on the December 2nd meeting,
00:11:24.600 --> 00:11:28.790
but if for some reason
this is what happens,
00:11:28.790 --> 00:11:30.680
we'll get it on the following one
00:11:30.680 --> 00:11:32.030
or have a budget next year.
00:11:33.720 --> 00:11:35.210
That's all I have to cover.
00:11:35.210 --> 00:11:39.290
And since there's no one else to speak,
00:11:39.290 --> 00:11:41.363
this meeting is closed.
00:11:41.363 --> 00:11:43.280
Thank you.
Thank you